1. Metering Installation at Normal Condition
Single Phase Meter and MCB |
Three Phase Meter and MCB |
Security seals of meter installations guarantee the safety of electricity supply installation, and should always be properly sealed under all circumstances. Please contact our Info Line 2833 9911 immediately if you find the meter damaged or the seal missing, broken or open.
2. Responsibilities
CEM
Install, exchange, seal and inspect meter
Customer
-
Prior application for any change of meter location and related electrical installations is required to be submitted to CEM. Unauthorized alteration is prohibited.
-
Do not arbitrarily switch off CEM's circuit breaker or interfere with the meter and electricity supply installation when the meter operates in normal conditions.
-
Maintain metering installation and it's located area in a safe and clean condition.
-
Do not use meter box or room area for any other usage. Make sure it remains accessible for CEM’s crew to enter and inspect.
-
All unit owner, residents, tenants and building management committee are obliged to maintain the communal electrical installations in buildings.
You can watch the following video (Chinse Only) to understand more about CEM & customer’s responsibility:
3. Safety Starts with You
Improper & Unsafe Conditions
Below are some conditions that largely affect the metering operation which may lead to electricity outage, and in the worst case, incidents like electric shock or fire hazard.
Meter room filled with objects blocking access for metering check and can easily catch fire |
Termite damaging the meter box/panel and wiring |
Broken meter cover |
Rotten meter board |
Non-display of reading due to circuit breaker next to the meter being switched off |
Fallen meter board |
If any of the above situations are detected:
|
Regular Check
In addition, regular check & maintenance of both in-house and communal electrical installations are important to enhance safety.
|